Analisa Manajemen Risiko Kesehatan Dan Keselamatan Kerja (K3) Pada Proyek Pembangunan Atap Rehabilitasi Puskesmas Kepuliungan Dengan Metode Hirarc
DOI:
https://doi.org/10.31004/koloni.v5i3.1157Keywords:
Occupational Health and Safety (OHS), HIRARC, Hazard Identification, Risk Assessment, Risk Control, Construction Project.Abstract
Occupational Health and Safety (OHS) is a crucial aspect of construction projects, particularly roof rehabilitation work, which carries a high risk of accidents. This study aims to identify hazards, analyze risk levels, and determine risk controls for the Kepulungan Community Health Center Roof Rehabilitation Project using the Hazard Identification, Risk Assessment, and Risk Control (HIRARC) method. A qualitative descriptive approach was employed, involving observations, interviews, documentation reviews, and a literature study with 15 respondents. The results indicate that the dominant hazards were falls from heights (100%) with a risk score of 25 (extreme), being struck by falling materials (93.33%) with a score of 16 (high), slips/trips (86.67%) with a score of 12 (high), cuts/lacerations (80%) with a score of 6 (moderate), and electric shock (73.33%) with a score of 12 (high). Implemented controls included the use of Personal Protective Equipment (100%), safety briefings (93.33%), standard-compliant scaffolding (86.67%), safety officer supervision (86.67%), and OHS signage (80%). Workers' perceptions yielded an average score of 4.21 ("agree"), indicating that OHS risk management implementation has been effective. However, improvements in training, supervision of work at heights, and fall protection systems are still required to minimize workplace accidents..References
Aini, N. (2022). Identifikasi bahaya dan pengendalian risiko dengan metode HIRARC. Skripsi. Universitas Sebelas Maret, Surakarta.
Fauzi, A. (2021). Analisis manajemen risiko K3 pada proyek konstruksi gedung. Skripsi. Universitas Negeri Yogyakarta, Yogyakarta.
Heizer, Jay dan Barry Render. 2006. Operations Management : Manajemen Operasi. Jakarta : Salemba Empat.
Hiller, Frederick S dan Lieberman,Gerald j.1990. Introduction to Operation Research. Fifth Edition. McGraw-Hill,Inc.Singapore
Hidayat, R., 2021. Evaluasi penerapan K3 pada proyek konstruksi bangunan gedung. Skripsi. Malang: Universitas Brawijaya.
ISO 45001. (2018). Occupational Health and Safety Management Systems.
Kerzner, Harold, (2006). “Project Management; A System Approach to Planning,
Scheduling and Control”, Van Nostrand Reinhald.Rahayu Puji Aryati, Mulyani Endang, Arpan Budiman. Analisa Percepatan Waktu Dengan Metode Fast Track Pada Proyek Konstruksi. Media Komunikasi Teknik Sipil 17. Hal 1 - 10.
Kholil, Muhammad. 2018.Scheduling of House Development Projects with CPM and PERT Method for Time Efficiency (Case Study: House Type 36. IOP Conf. Ser.: Earth Environ. Sci. 140 012010.
Lestari, D. (2020). Penerapan metode HIRARC untuk mengurangi risiko kecelakaan kerja. Skripsi. Universitas Diponegoro, Semarang.
Lerman, Henrique Fernando, Márcia de Fátima Morais, Camila Mato, Rodrigo Röde, Celise Röder. 2016. Optimization of Times and Costs of Project of Horizontal Laminator Production Using PERT/CPM Technical. Independent Journal of Management & Production, vol. 7, núm. 3, julio-septiembre, 2016, pp. 833-853.
Mahanavami, Gusti Ayu. Perencanaan Waktu Pelaksanaan Proyek Dengan Metode Pert (Studikasus Graha Miracle Denpasar)
Nurhayati, S. (2018). Analisis Risiko Kecelakaan Kerja dengan Metode HIRARC.
Pratama, R. (2019). Analisis risiko K3 pada proyek konstruksi menggunakan metode HIRARC. Skripsi. Universitas Muhammadiyah Surakarta, Surakarta.Ramli, S. (2010). Sistem Manajemen Keselamatan dan Kesehatan Kerja OHSAS 18001. Jakarta: Dian Rakyat.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Mochammad Arif, Khofifah Khofifah, Sucipto Sucipto

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.