Implementasi Building Information Modeling (BIM) 4D untuk Quantity Take-Off dan Visualisasi Penjadwalan pada Proyek Gedung Rumah Sakit Advent Manado

Authors

  • Matthew Restho Pakiding Politeknik Negeri Manado, Indonesia
  • Sherley Runtunuwu Politeknik Negeri Manado, Indonesia
  • Dwars Soukotta Politeknik Negeri Manado, Indonesia

DOI:

https://doi.org/10.31004/koloni.v5i4.1452

Keywords:

Building Information Modeling, BIM 4D, Quantity Take-Off, Autodesk Navisworks, Construction Scheduling.

Abstract

Building Information Modeling (BIM) 4D is an extension of BIM that integrates three-dimensional models with the time dimension to improve construction planning and Schedule visualization. This study aims to implement BIM 4D for the structural works of the Adventist Hospital Building Project in Manado through 3D modeling, Quantity Take-Off, scheduling, and construction simulation. A case study approach was employed using structural drawings, the Work Breakdown Structure (WBS), and the project Schedule as the primary data sources. The structural model was developed in Autodesk Revit 2025, the project Schedule was prepared in Microsoft Project, and the integration of geometry and time was performed in Autodesk Navisworks Manage using the TimeLiner feature. The results demonstrate that the BIM 3D model successfully represents all structural elements while automatically generating consistent quantity data. Furthermore, the integration of the model with the project Schedule produces a BIM 4D simulation that effectively visualizes the construction sequence according to planned activities, improving the understanding of task relationships and project progress. Therefore, the implementation of BIM 4D provides a more effective approach for planning, coordinating, and evaluating structural construction Schedules than conventional scheduling methods.

Downloads

Download data is not yet available.

References

Pantiga, J., & Soekiman, A. (2021). Kajian implementasi Building Information Modeling (BIM) di dunia konstruksi Indonesia. Rekayasa Sipil, 15(2), 104–110.

Mieslenna, C. F., & Wibowo, A. (2019). Mengeksplorasi penerapan Building Information Modeling (BIM) pada industri konstruksi Indonesia dari perspektif pengguna. Jurnal Sosial Ekonomi Pekerjaan Umum, 11(1), 44–58.

Prabowo, Y. S., & Hofifah, S. (2025). Penggunaan Navisworks Manage dan Microsoft Project untuk monitoring penjadwalan proyek konstruksi. Syntax Literate: Jurnal Ilmiah Indonesia, 10(5), 5460–5471.

Khatimi, H., & Pardosi, K. F. (2022). Implementasi Building Information Modeling 4D (Studi kasus: Proyek lanjutan pembangunan Gedung Kantor Sekretariat Daerah Kabupaten Tapin). Construction and Material Journal, 4(1), 1–10.

Fadhilah, A., Purwanto, E., & Basuki, A. (2022). Aplikasi Building Information Modeling (BIM) dalam perancangan bangunan gedung. Matriks Teknik Sipil, 10(3), 264–273.

Muin, O. E. A. (2022). Analisis jalur kritis penjadwalan proyek dengan metode Critical Path Method (CPM) menggunakan aplikasi Microsoft Project pada masa pandemi COVID-19 (Studi kasus pembangunan Gedung Kuliah Universitas Muhammadiyah Lamongan). Jurnal Extrapolasi, 19(1), 17–25.

Gustian, E., Milyardi, R., & Lesmana, C. (2022). Analysis of benefits and barriers factors in the implementation of Building Information Modeling (BIM) in building construction for contractor. Jurnal Teknik Sipil & Perencanaan, 25(2), 158–167.

Pradana, C. G., Vitria, A. H. P., & Fahrudin, D. M. (2025). Perbandingan pekerjaan arsitektur antara RAB proyek dengan BIM Cubicost pada Gedung Laboratorium ISI Surakarta. Jurnal Riset Rekayasa Sipil, 8(2), 46–53.

Wibowo, M. A., Hatmoko, J. U. D., & Satria, G. (2024). Implikasi integrasi BIM dan ERP terhadap pengendalian volume pekerjaan proyek: Studi kasus proyek bendungan. TEKNIK, 45(1), 128–138.

Isnubroto, D., & Putri, C. K. (2021). Analisis penjadwalan dan alokasi sumber daya pada proyek konstruksi menggunakan Microsoft Project (Studi kasus pekerjaan struktur Proyek XYZ). Wahana Teknik Sipil, 26(1), 52–65.

Praja, W. K., Hatmoko, J. U. D., & Hermawan, F. (2023). Penerapan evaluasi Building Information Modelling maturity di salah satu kontraktor BUMN Indonesia. CIVED: Journal of Civil Engineering and Vocational Education, 10(2), 693–707.

Soetjipto, J. W., Zarkasi, I. K., & Trisiana, A. (2023). Model perancangan pemeliharaan bangunan gedung menggunakan Building Information Modeling (BIM). Jurnal Permukiman, 18(1), 1–15.

Husin, A. E., & Sustiawan, F. (2021). Analisa Relative Important Index (RII) terhadap faktor-faktor yang berpengaruh dalam mengimplementasikan BIM 4D dan M-PERT pada pekerjaan struktur bangunan hunian bertingkat tinggi. Jurnal Aplikasi Teknik Sipil, 19(4), 417–426.

Pratama, A., & Marzuki, P. F. (2023). Kajian implementasi Building Information Modeling (BIM) di Indonesia berdasarkan perspektif pelaksana konstruksi (Studi kasus: Proyek kontraktor BUMN). Jurnal Teknik Sipil, 30(2), 277–296.

Hartono, W., Handayani, D., & Syafi’i. (2021). Tingkat kedewasaan penerapan Building Information Modelling (BIM) pada kontraktor jembatan di Indonesia. Jurnal Riset Rekayasa Sipil, 5(1), 50–61.

Downloads

Published

31-10-2026

How to Cite

Pakiding, M. R., Runtunuwu, S., & Soukotta, D. (2026). Implementasi Building Information Modeling (BIM) 4D untuk Quantity Take-Off dan Visualisasi Penjadwalan pada Proyek Gedung Rumah Sakit Advent Manado. KOLONI, 5(4), 4848–4858. https://doi.org/10.31004/koloni.v5i4.1452