Efektivitas Metode Fast Track Dalam Mempercepat Pelaksanaan Proyek Perkantoran Kairagi Mas Manado
DOI:
https://doi.org/10.31004/koloni.v5i4.1523Keywords:
project acceleration, Fast Track, Critical Path Method, critical path, time managementAbstract
Delays in construction project implementation can affect project success, so effective time acceleration efforts are needed. This study aims to analyze the acceleration of construction time on the Kairagi Mas Office Building Construction Project in Manado using the Fast Track method. The research used a quantitative approach with secondary data consisting of the time schedule, S-curve, and bill of quantities (RAB). The critical path was determined using the Critical Path Method (CPM) with the assistance of Microsoft Project, and activities on the critical path were then rearranged to overlap, with a maximum acceleration limit of 50% of the predecessor activity's duration. The analysis showed that the critical path consists of the foundation work through the LMR structure work, with a duration of 540 days. Of the nine pairs of activities analyzed, six pairs could be fully accelerated, while three pairs had already reached the maximum acceleration limit. After applying Fast Track, the critical path duration was reduced to 285 days, a reduction of 255 days (47.2%), and the overall duration of the structural work decreased from 432 days to 285 days (147 days or 34.0%). It can be concluded that the Fast Track method is effective in accelerating construction project implementation without adding labor or materials.Downloads
References
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Edisi 3, Yogyakarta
Perwitasari, D., Fahreza, A., & Ririh, K. R. (2021). “Analisis Percepatan Waktu Proyek Perumahan Menggunakan Metode PERT dan Fast Track.” RekaRacana: Jurnal Teknik Sipil, 7(1), 12–21. DOI: 10.26760/rekaracana.v7i1.226.
Srour, I. M., Abdul-Malak, M.-A. U., Yassine, A. A., & Ramadan, M. (2013). “A Methodology for Scheduling Overlapped Design Activities Based on Dependency Information.” Automation in Construction, 29, 1–11. DOI: 10.1016/j.autcon.2012.08.
Akhirudin, A. F. (2021a). PERCEPATAN WAKTU PENGERJAAN PROYEK KONSTRUKSI DENGAN MENGGUNAKAN METODE FAST TRACK. Jurnal Pendidikan Teknik Dan Vokasional, 3(2), 77–91. https://doi.org/10.21009/jptv.3.2.77
Akhirudin, A. F. (2021b). PERCEPATAN WAKTU PENGERJAAN PROYEK KONSTRUKSI DENGAN MENGGUNAKAN METODE FAST TRACK. Jurnal Pendidikan Teknik Dan Vokasional, 3(2), 77–91. https://doi.org/10.21009/jptv.3.2.77
Dahlan, A., Togi, I., Nainggolan, H., Ayu, R. L., & Winanda, S. T. (2019). EVALUASI PENGENDALIAN WAKTU DAN BIAYA MENGGUNAKAN METODE CRITICAL PATH METHOD (CPM) DAN FAST TRACK. 1.
Gede, I., Diputera, A., Putu, I., Hermawan, Y., Lidya, N. P., & Yanthi, M. (2023). ANALISIS WAKTU DAN BIAYA PERCEPATAN (FAST TRACK) PADA PEMBANGUNAN GEDUNG SKB KOTA DENPASAR BERBASIS SOFTWARE MICROSOFT PROJECT. Jurnal Ilmiah Kurva Teknik, 12(1). https://e-journal.unmas.ac.id/index.php/jikt
Lia Amelia Megawati, lirawati. (2020). ANALISIS FAKTOR KETERLAMBATAN ROYEK KONSTRUKSI BANGUNAN GEDUNG. 21(2).
Padma Arianie, G., & Budi Puspitasari, N. (2017). PERENCANAAN MANAJEMEN PROYEK DALAM MENINGKATKAN EFISIENSI DAN EFEKTIFITAS SUMBER DAYA PERUSAHAAN (Studi Kasus : Qiscus Pte Ltd). Jurnal Teknik Industri, 12(3).
Paharuddin, M. N. , A. I. A. (2024). MANAJEMEN Proyek (A. F. Andi Asari, Ed.).
Riadhus Solihin Adi, A. (2021). FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI GEDUNG Adriadi 1), Adi Riadhus Solihin ᶻ). Seminar Nasional Ketekniksipilan, Infrastruktur Dan Industri Jasa Konstruksi (KIIJK), 1(1).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Suiti Balandatu, Deyke Junita Femelia Mandang, Sudenroy Mentang

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.