Perbandingan Volume Dan Biaya Pekerjaan Struktur Metode Konvensional Dan BIM CUBICOST Pada Gedung Layanan Kesehatan Di Kota Manado
DOI:
https://doi.org/10.31004/koloni.v5i4.1538Keywords:
building information modeling, cubicost, quantity take-off, structural work, cost estimateAbstract
Calculating the quantity of structural work is the basis for preparing a project cost estimate, yet it is still commonly done manually from two-dimensional drawings. This study compares the volume of concrete, the weight of reinforcement, and the cost of structural work obtained from the conventional method and from Building Information Modeling (BIM) using Cubicost TAS and TRB. The case study is a multi-storey healthcare building in Manado, covering pile caps, columns, beams, and floor slabs. Both methods used the same working drawings, element totals were summed from floor-by-floor results, and the same unit prices were applied, so that cost differences arise only from differences in quantity. The results show that Cubicost produced smaller quantities for all elements. Total concrete volume was 10,085.89 m³ with Cubicost compared with 10,370.79 m³ with the conventional method (2.75% difference), and total reinforcement weight was 1,683,944.68 kg compared with 1,728,855.34 kg (2.60% difference). The largest concrete difference occurred in columns (5.37%) and the largest reinforcement difference in pile caps (3.58%). Total structural cost was Rp 35,630,590,081 with Cubicost and Rp 36,593,798,662 with the conventional method, a difference of Rp 963,208,581 (2.63%). Because no independent field validation was available, the results show differences between the methods and do not establish which one is more accurate.Downloads
References
Badan Standardisasi Nasional. (2019). Persyaratan beton struktural untuk bangunan gedung (SNI 2847:2019). Jakarta: Penulis.
Budiharto, N. (2025). Effectiveness of using building information modeling (BIM) in the Ministry of Health's UPT Vertical hospital project in Surabaya. Journal of Development and Integrated Engineering, 5(1), 19-26. doi:10.17509/jodie.v5i1.71872
Doumbouya, L., Gao, G., & Guan, C. (2016). Adoption of the building information modeling (BIM) for construction project effectiveness: The review of BIM benefits. American Journal of Civil Engineering and Architecture, 4(3), 74-79. doi:10.12691/ajcea-4-3-1
Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors (2nd ed.). Hoboken, NJ: John Wiley & Sons.
Fernando, R., Friatmojo, E. K., Ricardo, K. C., & Khairunnisa. (2024). Perbandingan quantity take-off baja tulangan antara metoda konvensional terhadap metoda BIM 5D Cubicost pada struktur gedung fasilitas perkeretaapian Manggarai. Orbith: Majalah Ilmiah Pengembangan Rekayasa dan Sosial, 20(1), 25-34. doi:10.32497/orbith.v20i1.5428
Herzanita, A., & Anggraini, R. P. (2023). Perbandingan estimasi biaya struktur bangunan antara software Autodesk Revit dengan Cubicost. Construction and Material Journal, 5(1), 1-11. doi:10.32722/cmj.v5i1.4620
Husen, A. (2011). Manajemen proyek: Perencanaan, penjadwalan, dan pengendalian proyek. Yogyakarta: Andi.
Hutama, H., & Sekarsari, J. (2018). Analisa faktor penghambat penerapan building information modeling dalam proyek konstruksi. Jurnal Infrastruktur, 4(1), 25-31.
Jonathan, R., & Anondho, B. (2021). Perbandingan perhitungan volume pekerjaan dak beton bertulang antara metode BIM dengan konvensional. Jurnal Mitra Teknik Sipil, 4(1), 271-280.
Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2018). Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 22/PRT/M/2018 tentang Pembangunan Bangunan Gedung Negara. Jakarta: Penulis.
Novita, R. D., & Pangestuti, E. K. (2021). Analisa quantity take off dan rencana anggaran biaya dengan metode building information modeling (BIM) menggunakan software Autodesk Revit 2019 (Studi kasus: Gedung LP3 Universitas Negeri Semarang). Dinamika Teknik Sipil: Majalah Ilmiah Teknik Sipil, 14(1), 27-31. doi:10.23917/dts.v14i1.15276
Olsen, D., & Taylor, J. M. (2017). Quantity take-off using building information modeling (BIM), and its limiting factors. Procedia Engineering, 196, 1098-1105.
Suwarni, A., & Anondho, B. (2021). Perbandingan perhitungan volume kolom beton antara building information modeling (BIM) dengan metode konvensional. JUTEKS: Jurnal Teknik Sipil, 6(2), 75-83. doi:10.32511/juteks.v6i2.743
Ulana, R., Sandi, E. A., & Hardiyanti, S. A. (2026). Perbandingan volume pembesian menggunakan metode konvensional dengan metode BIM pada proyek pembangunan Power House RSUD Ngudi Waluyo Wlingi Kabupaten Blitar. Jurnal Basement, 4(2), 147-159.
Wibisono, M. Y., Satwiko, P., & Suyoto. (2025). Implementasi BIM dengan software Glodon Cubicost dalam estimasi volume pekerjaan arsitektural. Vitruvian: Jurnal Arsitektur, Bangunan dan Lingkungan, 15(1), 59-70. doi:10.22441/vitruvian.2025.v15i1.006
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Farhan Hidayat, Deyke Junita Femeli Mandang, Steven Richard Kamurahan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.